A complete monthly reporting package, the way Torveen delivers it — owner summary first, then the schedules behind it. Open it and judge the work the way a banker would.
Owner Summary
The month in plain English — one page, first- Cash ended the month at $475,000, up $87,000. All three October draws were funded on schedule.
- The company earned $548,900 of revenue in October and $6,037,833 to date across four jobs, at a gross margin of 13.2%.
- Riverton Phase 2 is on budget overall: concrete is running $19,600 over, more than covered by savings in framing.
- Billing is keeping pace with the work. Work completed and awaiting its next draw totals $137,833, and no job is billed ahead of progress.
- Retainage held on completed work totals $248,000. Hillcrest’s $32,000 releases on final sign-off, expected next month.
- Looking ahead: draws of $615,000 are scheduled over the next four weeks against expected payouts of about $520,000, and the credit line is fully undrawn.
WIP Schedule
Through October 31, 2026 · All figures in dollars| Job | Contract | Costs to date | Est. to complete | Total est. cost | % complete | Earned revenue | Billed to date | Over / (Under) billed | Gross profit earned |
|---|---|---|---|---|---|---|---|---|---|
| 2411 Riverton Estates — Phase 2 | 4,850,000 | 2,800,000 | 1,400,000 | 4,200,000 | 66.7% | 3,233,333 | 3,150,000 | (83,333) under | 433,333 |
| 2414 Northgate Retail Shell | 2,340,000 | 1,640,000 | 410,000 | 2,050,000 | 80.0% | 1,872,000 | 1,840,000 | (32,000) under | 232,000 |
| 2417 Maple Street Custom Home | 975,000 | 253,500 | 591,500 | 845,000 | 30.0% | 292,500 | 270,000 | (22,500) under | 39,000 |
| 2409 Hillcrest Tenant Improvement (complete) | 640,000 | 550,000 | 0 | 550,000 | 100% | 640,000 | 640,000 | 0 | 90,000 |
| Totals | 8,805,000 | 5,243,500 | 2,401,500 | 7,645,000 | — | 6,037,833 | 5,900,000 | (137,833) under | 794,333 |
Percent complete = costs to date ÷ total estimated cost. Earned revenue = percent complete × contract price. Under-billed work is work performed but not yet billed. No job is billed in excess of work performed. Backlog remaining to earn: $2,767,167.
Budget-to-Actual
Job 2411 Riverton Estates Phase 2 · Through October 31, 2026| Cost code | Budget | Actual | Variance |
|---|---|---|---|
| Sitework | 540,000 | 512,300 | 27,700 under |
| Concrete | 730,000 | 749,600 | (19,600) over |
| Framing & lumber | 1,020,000 | 965,700 | 54,300 under |
| MEP rough-in | 830,000 | 572,400* | in progress |
| Finishes | 1,080,000 | 0 | not started |
| Total estimated cost | 4,200,000 | 2,800,000 |
*MEP actual is spending to date on work in progress, not a completed variance. Note: concrete is running $19,600 over budget — the second pour's unit prices came in above the bid. Framing savings of $54,300 more than cover the overage, and the job's total estimated cost is unchanged.
Cash View
October 2026, and the four weeks aheadFinancial Snapshot
October 2026 · Year to date · Balance sheet at October 31, 2026Income Statement — October 2026
Year to Date
Balance Sheet — Oct 31, 2026
This is the package every Torveen client gets each month — yours would carry your jobs, your numbers.